M.D. council demands advance warning on major capital budget overruns

The Municipal District of Opportunity council has passed a new finance policy that requires municipal staff to get council’s permission before spending extra money on major capital project cost overruns.

During its Oct. 26 meeting in Wabasca, council unanimously approved Policy F.20, the Capital Project Overage Policy, after adding a strict rule that any overrun above $10,000 must come to the council table before the work is authorized or the bill is paid.

The policy, drafted by Director of Finance Ryan Musch and presented by Chief Administrative Officer Chad Tullis, was originally brought forward to speed up how the M.D. handles minor extra costs at the end of a construction project.

Under Section 248(1) of Alberta’s Municipal Government Act, “a municipality may only make an expenditure that is (a) included in an operating budget, interim operating budget or capital budget or otherwise authorized by the council, (b) for an emergency, or (c) legally required to be paid.”

Because of that provincial law, even tiny budget overruns previously had to wait for a formal council vote. Under the new policy, the chief administrative officer can approve small capital project overruns of up to 10 per cent of the project’s budget, to a maximum of $10,000. Any small overages approved by the chief administrative officer must still be tracked by the finance department and reported to council in monthly updates.

“Instead of having to come to council when we’re $100 over on a capital project, this allows the CAO to approve 10 per cent or a maximum of $10,000 overage on capital,” Tullis said. “Instead of having to come for a resolution when we’re literally $100 over, it just makes the process a little bit more streamlined.”

While councillors had no issue letting administration sign off on small overruns, Deputy Reeve Brendan Powell said the policy needed a clear rule forcing staff to bring larger overruns to council before the money is spent.

“We’ve had several projects go over budget—more than several—by $10,000, $20,000, $100,000,” Powell said. “I just think that needs to be approved before it’s actually spent. Because we have meetings every two weeks, if there’s ever going to be a large amount over budget, we should know beforehand, and the reason behind it.”

Tullis said administration never wants projects to go over budget, noting that out of 30 municipal projects, 28 might come in under budget while two go over due to outside pressures like tariffs or unexpected change orders. While staff try to bring budget adjustments to council in advance, Tullis said surprise invoices can still happen.

“The reality is I can’t guarantee 100 per cent of the time that we’ll never have an overage, that we don’t get an invoice and go, ‘Oh shoot, we’re over,’” Tullis said. “It’s not an ideal situation and we try to avoid that.”

Reeve Marshall D. Auger backed Powell’s call for tighter oversight, saying department directors need to stay on top of their project budgets at all times.

Councillor Robin Guild noted that the written policy was designed to streamline small bills under $10,000, while Powell’s concern was aimed at stopping large runaway costs.

Councillor Gerald Johnson asked how the rule would work in practice to make sure contractors do not complete extra work before council approves the added cost.

Powell explained that when council only finds out about a massive overrun months after the work is finished, elected officials have no choice but to pay the bill.

“If we approve a budget for whatever project for $100,000, and the project starts and continues, and then come October we have to do a budget amendment because we find out that project is now $180,000 or $150,000—that should be brought to our attention as it’s going through the year,” Powell said. “If that happened in the summer, then it needs to come to us right away, because our hands are tied after the job is done. Our hands are tied, and the only thing we can control is policy.”

To address council’s concern, Tullis wrote a new clause into the policy stating: “Any overage exceeding CAO thresholds shall come to council for approval in advance of authorized spending.”

Tullis explained that using the phrase “authorized spending” means municipal staff cannot sign a contractor change order, approve extra work, or pay an invoice that pushes a project past the chief administrative officer’s $10,000 limit without getting council’s approval first.

Powell made a motion to approve the Capital Project Overage Policy with the added wording, which council passed unanimously.

Armaan Khanna 

Local Journalism Initiative Reporter