M.D. expands fibre internet network

The Municipal District of Opportunity No. 17 is bringing high-speed fibre optic internet to 10 public facilities in Calling Lake and Sandy Lake, a move expected to modernize local communications and save the municipality money over the next few decades.

During a regular council meeting on Sept. 28 in Red Earth Creek, the municipal council unanimously approved a $20,350 capital budget amendment to connect the civic buildings to a new, hardwired fibre network.

Director of Finance Ryan Musch presented the project to the council, stating that the municipality is partnering with Arrow Technology Group for the installations. Musch explained that Arrow agreed to provide the majority of the fibre optic cable installations complimentarily because their crews are already working in those specific areas.

As a result of the partnership, the municipality only needs to pay $250 per site for the terminal equipment and network activation, totalling $2,500 for the 10 buildings. The list of facilities scheduled for the upgrade includes community complexes, local arenas, water treatment plants, and fire halls in both hamlets.

“Really good news for us,” Musch said during the meeting, referring to the unusually low installation cost per unit.

However, setting up a safe and secure network across multiple government buildings requires a bit more upfront investment. Musch said an additional $17,850 is needed to install specialized firewalls, establish secure virtual private network connections, and purchase the first year of security software for the facilities. This brought the total approved funding to $20,350, which will be drawn from the municipality’s unrestricted reserves.

The technology upgrade is also being framed as a strategic financial decision for the region. During the meeting, Councillor Darlene Jackson asked what internet service the municipal public works shops are currently using. Administration clarified that they are currently relying on Starlink satellite internet dishes.

Musch recommended that the municipality avoid setting up any more Starlink connections moving forward. By switching public facilities to a hardwired fibre optic network, the local government can completely eliminate the expensive recurring monthly fees associated with the satellite service. He emphasized to the council that laying down fibre optics will serve as a solid 20- to 30-year investment for the region.

Furthermore, the meeting discussions revealed that the municipality’s current security systems are not running optimally on the existing, slower network units. The new high-speed connections are expected to finally resolve those lagging performance issues and ensure public facilities remain secure.

Following the presentation, Councillor Robin Guild made a motion to accept the administration’s recommendation to fund the 10 building connections. The motion was put to a vote and carried by the council without any opposition.

While the current project focuses strictly on 10 specific sites in Calling Lake and Sandy Lake, the expansion will not stop there. Municipal staff are actively compiling a list of remaining office facilities, including those in Red Earth Creek, to bring forward to the council for future internet upgrades.